Homeowner basics

How to Read a Bid or Estimate

What a good bid includes, how to compare three bids fairly, what 'allowance' and 'exclusion' mean, and the missing items that cause surprise costs.

Checkmarks are saved only in this browser.

The parts of a good bid

Comparing bids apples-to-apples

  1. Make a simple table with one row per item (demo, framing, plumbing, fixtures, permit...) and one column per contractor.
  2. Mark each item 'included', 'excluded' or 'allowance $___'.
  3. Add the cost of anything excluded to that bid so totals compare fairly.
  4. Be wary of the lowest bid if it is missing items the others include.
  5. Ask each contractor to explain big differences.

Words you'll see

  • Allowance - a placeholder budget for items you'll pick later. If you pick something pricier, you pay the difference.
  • Exclusion - work the contractor is not doing or pricing.
  • Change order - a written, signed change to scope and price after signing.
  • Contingency - money set aside for surprises (some bids include it; you can also keep your own).
  • Markup/overhead & profit - the contractor's cost of running the business and earning a living. It is normal and legitimate.
  • T&M (time and materials) - you pay actual hours and materials, usually with a cap you should insist on.

Commonly missing items

  • Permit fees and inspections
  • Disposal/dumpster
  • Drywall patch and paint after plumbing or electrical
  • Trim and transitions
  • Repairs found during demo (ask for unit prices)
  • Appliance hookups
  • Cleanup

Please note

Educational information only - not legal, engineering or code advice. Rules vary by state, county and city, and change over time. Check with your local building department and licensing board, and read your own contract.